<?xml version="1.0" encoding="UTF-8"?>
<?xml-stylesheet type="text/xsl" href="https://reports-public-sandbox.ieso.ca/docrefs/stylesheet/RealtimeTotals_HTML_t1-1.xsl" ?>
<Document docID="RealtimeTotals" xmlns="http://www.ieso.ca/schema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.ieso.ca/schema https://reports-public-sandbox.ieso.ca/docrefs/schema/RealtimeTotals_r1.xsd">
<DocHeader>
<DocTitle>Realtime Totals Report</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-03-26T07:59:49</CreatedAt>
</DocHeader>
<DocBody>
<DeliveryDate>2026-03-26</DeliveryDate>
<DeliveryHour>8</DeliveryHour>
<Energies>
<IntervalEnergy>
<Interval>1</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12377.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>363.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12014.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>541.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>100</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18261.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>2</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12274.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>357.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11916.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>597.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>100</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>15.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18221.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>3</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12747.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>383.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12363.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>608.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>100</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18062.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>4</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12865.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>387.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12478.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>608.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>100</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18191.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>5</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12739.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>380.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12358.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>608.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>25.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18083.3</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>6</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12704.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>376.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12328.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>561.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18192.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>7</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12390.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>360.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12030.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>561.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>100</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18138.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>8</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12475.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>364.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12110.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>561.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18117.7</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>9</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12035.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>344.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11691</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>300.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18414.5</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>10</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12572.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>366.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12205.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>608.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>79</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18012.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>11</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12479.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>363.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12115.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>562.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18060.3</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>12</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12417.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>361.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12056</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>562.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>60</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>18005.2</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
</Energies>
</DocBody>
</Document>