<?xml version="1.0" encoding="UTF-8"?>
<?xml-stylesheet type="text/xsl" href="https://reports-public-sandbox.ieso.ca/docrefs/stylesheet/RealtimeTotals_HTML_t1-1.xsl" ?>
<Document docID="RealtimeTotals" xmlns="http://www.ieso.ca/schema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.ieso.ca/schema https://reports-public-sandbox.ieso.ca/docrefs/schema/RealtimeTotals_r1.xsd">
<DocHeader>
<DocTitle>Realtime Totals Report</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-04-10T11:52:50</CreatedAt>
</DocHeader>
<DocBody>
<DeliveryDate>2026-04-10</DeliveryDate>
<DeliveryHour>12</DeliveryHour>
<Energies>
<IntervalEnergy>
<Interval>1</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12445.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>310.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12134.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>623.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17255.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>2</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12299.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>308.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11990.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17278.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>3</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12293.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>311.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11981.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17275.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>4</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12299.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>313.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11985.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17516.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>5</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12303.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>314.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11988.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17474.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>6</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12308.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>314.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11994.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17505.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>7</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12300.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>313</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11987.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17372.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>8</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12306</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>313.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11992.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17405.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>9</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12306.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>313</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11993.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17339.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>10</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12318.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>313.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12005.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17222.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>11</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12321</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>312.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>12008.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17273.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>12</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>12291.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>311.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>11980.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>612.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>0</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>105.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>17277.9</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
</Energies>
</DocBody>
</Document>