<?xml version="1.0" encoding="UTF-8"?>
<?xml-stylesheet type="text/xsl" href="https://reports-public-sandbox.ieso.ca/docrefs/stylesheet/RealtimeTotals_HTML_t1-1.xsl" ?>
<Document docID="RealtimeTotals" xmlns="http://www.ieso.ca/schema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.ieso.ca/schema https://reports-public-sandbox.ieso.ca/docrefs/schema/RealtimeTotals_r1.xsd">
<DocHeader>
<DocTitle>Realtime Totals Report</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-05-12T02:59:51</CreatedAt>
</DocHeader>
<DocBody>
<DeliveryDate>2026-05-12</DeliveryDate>
<DeliveryHour>3</DeliveryHour>
<Energies>
<IntervalEnergy>
<Interval>1</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9513.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>264</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9249.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>50.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>523.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13448.7</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>2</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9513.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>264</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9249.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>50.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>523.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13448.7</EnergyMW>
</MQ>
<Flag>ADMIN</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>3</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9571.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>258.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9313.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>50.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>500</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13607</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>4</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9571.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>258.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9313.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>50.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>500</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13607</EnergyMW>
</MQ>
<Flag>ADMIN</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>5</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9626.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>264.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9362.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>76.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>376</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13414.1</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>6</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9626.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>264.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9362.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>76.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>376</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13414.1</EnergyMW>
</MQ>
<Flag>ADMIN</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>7</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9504.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>257</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9247.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>50.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>497.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13391.4</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>8</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9504.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>257</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9247.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>50.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>497.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13391.4</EnergyMW>
</MQ>
<Flag>ADMIN</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>9</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9561.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>250.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9311</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>76.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>371.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13117.2</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>10</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9561.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>250.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9311</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>76.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>371.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13117.2</EnergyMW>
</MQ>
<Flag>ADMIN</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>11</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9477.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>265.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9212.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>76.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>495</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13163.6</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>12</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>9477.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>265.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>9212.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>872.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>120</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>76.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>495</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>13163.6</EnergyMW>
</MQ>
<Flag>ADMIN</Flag>
</IntervalEnergy>
</Energies>
</DocBody>
</Document>
