<DocHeader>
<DocTitle>Planned Transmission Outages Occurring Next 30 Days</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-08-20T06:20:49</CreatedAt>
</DocHeader>
<DocBody>
<OutageRangeStart>2026-08-20T00:00:00</OutageRangeStart>
<OutageRangeEnd>2026-09-18T23:59:59</OutageRangeEnd>
<OutageRequest>
<OutageID>1-00144538</OutageID>
<PlannedStart>2025-03-10T07:00:00</PlannedStart>
<PlannedEnd>2027-12-10T17:00:00</PlannedEnd>
<Priority>P</Priority>
<Recurrence>C</Recurrence>
<EquipmentRequested>
<EquipmentName>KAKABEKA FALLS GS T1</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRequested>
<EquipmentName>KAKABEKA FALLS GS T2</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRequested>
<EquipmentName>KAKABEKA FALLS GS T3</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRequested>
<EquipmentName>KAKABEKA FALLS GS T4</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRecallTime>Non-recallable</EquipmentRecallTime>
<OutageRequestStatus>AA</OutageRequestStatus>
</OutageRequest>
<OutageRequest>
<OutageID>1-00245787</OutageID>
<PlannedStart>2026-09-08T07:00:00</PlannedStart>
<PlannedEnd>2026-09-18T16:00:00</PlannedEnd>
<Priority>P</Priority>
<Recurrence>C</Recurrence>
<EquipmentRequested>
<EquipmentName>CHATS FALLS GS T30-Q4C</EquipmentName>
<EquipmentType>Disconnect</EquipmentType>
<EquipmentVoltage>230 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRequested>
<EquipmentName>CHATS FALLS GS TSS2</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRecallTime>1 Day(s)</EquipmentRecallTime>
<OutageRequestStatus>RISK</OutageRequestStatus>
</OutageRequest>
<OutageRequest>
<OutageID>1-00247612</OutageID>
<PlannedStart>2026-09-16T08:00:00</PlannedStart>
<PlannedEnd>2026-09-16T16:00:00</PlannedEnd>
<Priority>P</Priority>
<Recurrence>C</Recurrence>
<EquipmentRequested>
<EquipmentName>ARNPRIOR GS TSS1</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRecallTime>1 Hour(s)</EquipmentRecallTime>
<OutageRequestStatus>RISK</OutageRequestStatus>
</OutageRequest>
<OutageRequest>
<OutageID>1-00249610</OutageID>
<PlannedStart>2024-03-15T08:00:00</PlannedStart>
<PlannedEnd>2027-12-31T23:00:00</PlannedEnd>
<Priority>I</Priority>
<Recurrence>C</Recurrence>
<EquipmentRequested>
<EquipmentName>LAKEHEAD TS C8A</EquipmentName>
<EquipmentType>Breaker</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>INFO</ConstraintType>
</EquipmentRequested>
<EquipmentRecallTime>Non-recallable</EquipmentRecallTime>
<OutageRequestStatus>IMPL</OutageRequestStatus>
</OutageRequest>
<OutageRequest>
<OutageID>1-00249895</OutageID>
<PlannedStart>2026-09-14T08:00:00</PlannedStart>
<PlannedEnd>2026-09-15T15:00:00</PlannedEnd>
<Priority>P</Priority>
<Recurrence>C</Recurrence>
<EquipmentRequested>
<EquipmentName>SMOKY FALLS 2 GS SS1</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRecallTime>6 Hour(s)</EquipmentRecallTime>
<OutageRequestStatus>RISK</OutageRequestStatus>
</OutageRequest>
<OutageRequest>
<OutageID>1-00250625</OutageID>
<PlannedStart>2026-09-14T07:00:00</PlannedStart>
<PlannedEnd>2026-09-15T16:00:00</PlannedEnd>
<Priority>P</Priority>
<Recurrence>C</Recurrence>
<EquipmentRequested>
<EquipmentName>OTTO HOLDEN GS SS2</EquipmentName>
<EquipmentType>PowerTransformer</EquipmentType>
<EquipmentVoltage>50 kV</EquipmentVoltage>
<ConstraintType>OOS</ConstraintType>
</EquipmentRequested>
<EquipmentRecallTime>Non-recallable</EquipmentRecallTime>
<OutageRequestStatus>RISK</OutageRequestStatus>
</OutageRequest>
</DocBody>